The reef was closed during the summer of 2011 having been closed for safety reasons in March, in July Bournemouth Councillor Rod Cooper, Cabinet Member for Economy & Tourism announced that ASR ltd would undertake the repair work and begin the improvement work in early August.

This is progressing well and the reef will form an integral part of the Coastal Activity Park, which is scheduled to open in Spring 2014.”.

Bournemouth council received £306,531 in respect of two insurance claims for damage to the reef, the council's intention being to repair the reef to its original condition and reopen it in April 2014.

A study undertaken for Bournemouth council shows that prior to the reef there were 77 good surfing days annually, although surfing took place on 153 days, with a total of 5,000 surf visits to Boscombe per year.

The intention was that the reef would double the number of good surfing days and it was hoped this would generate 10,000 visits.

In December 2010 Bournemouth Council announced that ASR would return in the spring of 2011 to make modifications to the reef.

Four bags were to be situated on the south-east corner of the reef and a further three pillow bags between existing sections of the reef.

Like most of the other reefs built to date, the Boscombe Reef was built from large sand-filled geotextile containers.

With a total volume of 13,000 m, the reef was designed purely as a surfing break.

Historical data is available to ABC members and paid subscribers.

Please log in if you are one of these or sign up to one of our subscriptions.

Please log in or sign up to one of our subscriptions.

Tags: , ,